UNOLS Ship Time Request Form - Section ONE
===============================================================================
UNOLS Request ID #: 20030602135805RF
Version #: 004
Last Modified: 2006/03/15 16:54 EST
Date Issued: 2009/11/23 01:26 EST
===============================================================================
P.I. Name Last: Chaffey First: Mark MI: R
===============================================================================
Institution: MBARI Research vessel required for:
Address: 7700 Sandholdt Road _ Ancillary Only
Moss Landing, CA X Principal Use
_ No Ship Required
_ Long Range Planning Document
===============================================================================
Phone: 831 775 1708 Fax: 831 775 1646 Email: chma@mbari.org
===============================================================================
Co P.I. Name Institution Co P.I. Name Institution
------------ ----------- ------------ -----------
Keith Raybould MBARI Andrew Hamilton MBARI
===============================================================================
Proposal Title:
---------------
Collaborative Research: Design, Modeling, and Testing of Electro-Optic
Mechanical (EOM) Mooring Cables for Moored-Buoy Observatories
===============================================================================
Large Program Name: None Research Purpose: Instrumentation
If Other, specify: If Other, specify:
===============================================================================
New Proposal? N Agency Submitted to: Foreign EEZ? N
Funded Grant? Y NSF/OCE/OTIC
Institutional Proposal #: Amount Requested: Area(s) of Operation:
648,550 NP9
Agency Proposal #:
6254964 Lat/Long:
Renewal? N Start Date: 10/01/2003 Begin: 36.824N, 122.275W
Grant #: End Date: 09/30/2006 End: 36.824N, 122.275W
===============================================================================
Ship(s) Requested # Science
Year (Name or Size) Days Req. Optimum Dates Alternate Dates
---- ----------------- --------- ------------- ---------------
2005 Point Sur 2 9/26/05 9/27/06
2006 Point Sur 1 6/28/06 6/28/06
2006 Point Sur 2 9/15/06 11/15/06
===============================================================================
Total Science & Ship Days Needed: --------------- PORTS ------------
5 Start: Intermediate: End:
Number in Science Party: Moss Landing NA Moss Landing
8
===============================================================================
Equipment Required:
_ Vans _ P-Code GPS _ MCS _ Alvin _ ABE
_ Dynamic Positioning _ Multibeam _ SCS _ ROV _ 680 Cond.
_ Helicopter Operation
===============================================================================
Other Special Equipment; Comments:
----------------------------------
Large Oceanographic winch supplied by MBARI
===============================================================================