R/V ROV 2006 FINAL Schedule
=======================================================================
01/04: changed pending programs to funded
10/5: Changed dates for JII test cruise on KM
9/26: Added 2 days to Moyer cruise, shifted KM test cruise 2 days later.
7/7: Added 2 days to Taylor ROV test cruise.
6/16: Added 3 days to Fisher Sept cruise. Shifted following cruises
later.
3/20: Added 10 days to Bach/Tivey
2/23: Removed Bowen days and updated crusie dates
1/06: Removed second 30 day McDonough/NOAA cruise
1/06: Moved Moyer and Taylor cruises earlier.
12/08: Added dates for Taylor JII test cruise in Dec.
11/14: Changed cruise dates to avoid Easter holiday in Guam.
11/1: Changed in-port mob days for Bach
10/21: Changed JII mob and eng dive from San Diego to Guam.
10/21: Shifted dates of all programs to match updated Melville sched.
10/3: Changed Bach loading to Yokohama 2-5 July, total days 38.
10/3: Decreased McDonough/NOAA Sept. cruise to 30 days.
=======================================================================
DAYS/AGENCY/
CRUISE MAP INDEX/AREA/ P.I./INSTITUTION/ PORTS STATUS/
DATES PURPOSE PROPOSAL NO. CLEARANCE
=======================================================================
01 JAN SP3A/Galapagos/ Haymon, R./UCSB/ Galapagos 11/NSF/F
10 JAN Medea & DSL-120 OCE-0324668 Galapagos
11
Thompson 2005-06. DSL-120 is using Medea. Medea will need to be shipped to
meet JII. 1 week to reconfigure with JII again. Medea will be offloaded from
Thompson in Papeete Feb. 10-11th and shipped to Guam to meet Melville.
----------
14, 15, 16, 17
18 APR NP10/Ring of Fire/ McDonough, J./NOAA Apra, Guam 31/NOAA/F
13 MAY Jason II Ocean Explor/NOAA Yokohama
/NP10/ Bowen, A./WHOI/ 1/NOAA/F
Jason II Eng dive NA
14, 15
R/V Melville. Jason II Bob Embley-chief scientist robert.w.embley@noaa.gov.
This assumes one day engineering test for DSL on the 18th. Jason II will need
to be offloaded in Yokohama, May 14-17th. Gear not onboard during Watts cruise,
18 May to 05 July. JII will need to be loaded back on in Yokohama July 8-10th.
----------
08 JUL IN5/In Port MOB/ Bach, W./WHOI/ Yokohama 3/NSF/F
10 JUL Jason II 0327448 Yokohama
In-Port Mobilization of Jason II onto R/V MELVILLE, 8-10 July in Yokohama. Ship
departs on afternoon of July 10th. July 10-19th Transit Yokohama to Rabaul PNG
for personnel pick up. 1 port days in Rabaul on July 20th.
----------
20
21 JUL IN5/Manus Basin/ Bach, W./WHOI/ Rabaul PNG 35/NSF/F
01 SEP Jason II 0327448 Suva PNG
NP10/3deg 10'S,150/ Bach/Tivey/WHOI/ 10/Other/F
Survey in Vienna Woods NA
2
R/V Melville. Jason II. 24 sci., transit 7, plus 4 port, 1.5 arr/dep. 10 days
sci. added for pending charter; JII will need to be loaded back on in Yokohama.
Port days 8-10 July in Yokahama. July 10-19th Transit Yokahama to Rabaul PNG
for personnel pick up.
Intermediate port stop in Kavieng, PNG on July 30.
Maurice Tivey, Chief Scientist
----------
3, 4
05 SEP SP1/Lau Basin/ Fisher, C./Penn Suva 26/NSF/F
02 OCT Jason II State/OCE-0240982 Suva Tonga
SP1/Lau Basin/ Cavanaugh, C./Harv 2/NSF/F
Jason II ard/OCE-0453901
NP9/Off Fiji/ Fisher, C./Penn St 3/Other/F
multibeam at/Fiji government
3
R/V Melville. Jason II. sci.-17, port-3 transit-4 plus 1.5. 3 days for Fiji
govenment.
Chuck Fisher, Chief Sci.
Melville transit Suva to Honolulu 11- 20 Oct.
----------
21,22,23
24 OCT NP12/19N 155W/ Moyer, C./WWU/ Honolulu 20/NSF/F
12 NOV Jason II MCB-0348734 Honolulu
NP12// Bowen, A./WHOI/ 1/NSF/F
Jason II Eng dive NSF
NP12/Off Big Island/ McGuire, J/WHOI/ 2/NSF/F
OBS recovery OCE
R/V Melville. Jason II.
14 sci.,, (extra port day added for Navy fueling), 3 transit,
1 day for engineering dive.
----------
13, 14, 15
16 NOV NP12// Taylor, B./UHI/ Honolulu 9/Other/F
20 NOV Jason II Test cruise UHI Honolulu
21
R/V Kilo Moana. Jason II test cruise. 4 ops, 4 port. Details of test cruise
have not been finalized. KM underway 0800 16 November and a return 0800 20
November. Four days underway; nine calendar days (16-21 Nov) required on
schedule
due to on-load and off-load requirements.
----------
Agency Funded Proposed TOTAL
------ ------ -------- -----
NOAA 32.0 0.0 32.0
NSF 100.0 0.0 100.0
Other 22.0 0.0 22.0
------ ----- ----- -----
TOTAL 154.0 0.0 154.0