POC:  Liz Caporelli                       LAST UPDATED: 2007/01/04 16:35 EST
        Marine Operations
      Woods Hole Oceanographic Institution
      38 Water St.
      Mail Stop-37
      Tel: 508-289-2277
      Fax: 508-457-2185
      Email: ecaporelli@whoi.edu

                         R/V ROV 2006 FINAL Schedule

=======================================================================
01/04: changed pending programs to funded
10/5: Changed dates for JII test cruise on KM
9/26: Added 2 days to Moyer cruise, shifted KM test cruise 2 days later.
7/7: Added 2 days to Taylor ROV test cruise.
6/16: Added 3 days to Fisher Sept cruise. Shifted following cruises
later.
3/20: Added 10 days to Bach/Tivey
2/23: Removed Bowen days and updated crusie dates
1/06: Removed second 30 day McDonough/NOAA cruise
1/06: Moved Moyer and Taylor cruises earlier.
12/08: Added dates for Taylor JII test cruise in Dec.
11/14: Changed cruise dates to avoid Easter holiday in Guam.
11/1: Changed in-port mob days for Bach
10/21: Changed JII mob and eng dive from San Diego to Guam.
10/21: Shifted dates of all programs to match updated Melville sched.
10/3: Changed Bach loading to Yokohama 2-5 July, total days 38.
10/3: Decreased McDonough/NOAA Sept. cruise to 30 days.
=======================================================================
                                                              DAYS/AGENCY/
CRUISE  MAP INDEX/AREA/        P.I./INSTITUTION/  PORTS       STATUS/
DATES   PURPOSE                PROPOSAL NO.                   CLEARANCE
=======================================================================
01 JAN  SP3A/Galapagos/        Haymon, R./UCSB/   Galapagos   11/NSF/F
10 JAN  Medea & DSL-120        OCE-0324668        Galapagos             
11                                                                      
Thompson 2005-06. DSL-120  is using Medea. Medea will need to be shipped to
meet JII. 1 week to reconfigure with JII again. Medea will be offloaded from
Thompson in Papeete Feb. 10-11th and shipped to Guam to meet Melville.
----------

14, 15, 16, 17
18 APR  NP10/Ring of Fire/     McDonough, J./NOAA Apra, Guam  31/NOAA/F
13 MAY  Jason II                Ocean Explor/NOAA Yokohama              
        /NP10/                 Bowen, A./WHOI/                1/NOAA/F
        Jason II Eng dive      NA                                       
14, 15
R/V Melville.  Jason II  Bob Embley-chief scientist  robert.w.embley@noaa.gov.
This assumes one day engineering test for DSL on the 18th. Jason II will need
to be offloaded in Yokohama, May 14-17th. Gear not onboard during Watts cruise,
18 May to 05 July. JII will need to be loaded back on in Yokohama July 8-10th.
----------

08 JUL  IN5/In Port MOB/       Bach, W./WHOI/     Yokohama    3/NSF/F
10 JUL  Jason II               0327448            Yokohama              
In-Port Mobilization of Jason II onto R/V MELVILLE, 8-10 July in Yokohama. Ship
departs on afternoon of July 10th. July 10-19th Transit Yokohama to Rabaul PNG
for personnel pick up. 1 port days in Rabaul on July 20th.
----------

20
21 JUL  IN5/Manus Basin/       Bach, W./WHOI/     Rabaul PNG  35/NSF/F
01 SEP  Jason II               0327448            Suva        PNG       
        NP10/3deg 10'S,150/    Bach/Tivey/WHOI/               10/Other/F
        Survey in Vienna Woods NA                                       
2
R/V Melville. Jason II.  24 sci., transit 7, plus 4 port, 1.5 arr/dep. 10 days
sci. added for pending charter; JII will need to be loaded back on in Yokohama.
Port days 8-10 July in Yokahama. July 10-19th Transit Yokahama to Rabaul PNG
for personnel pick up.
Intermediate port stop in Kavieng, PNG on July 30.
Maurice Tivey, Chief Scientist
----------

3, 4
05 SEP  SP1/Lau Basin/         Fisher, C./Penn    Suva        26/NSF/F
02 OCT  Jason II               State/OCE-0240982  Suva        Tonga     
        SP1/Lau Basin/         Cavanaugh, C./Harv             2/NSF/F
        Jason II               ard/OCE-0453901                          
        NP9/Off Fiji/          Fisher, C./Penn St             3/Other/F
        multibeam              at/Fiji government                       
3
R/V Melville. Jason II.  sci.-17, port-3 transit-4 plus 1.5. 3 days for Fiji
govenment.
Chuck Fisher, Chief Sci.
Melville transit Suva to Honolulu 11- 20 Oct.
----------

21,22,23
24 OCT  NP12/19N 155W/         Moyer, C./WWU/     Honolulu    20/NSF/F
12 NOV  Jason II               MCB-0348734        Honolulu              
        NP12//                 Bowen, A./WHOI/                1/NSF/F
        Jason II Eng dive      NSF                                      
        NP12/Off Big Island/   McGuire, J/WHOI/               2/NSF/F
        OBS recovery           OCE                                      
R/V Melville. Jason II.
14 sci.,, (extra port day added for Navy fueling), 3 transit,
1 day for engineering dive.
----------

13, 14, 15
16 NOV  NP12//                 Taylor, B./UHI/    Honolulu    9/Other/F
20 NOV  Jason II Test cruise   UHI                Honolulu              
21                                                                      
R/V Kilo Moana. Jason II test cruise.  4 ops, 4 port. Details of test cruise
have not been finalized. KM underway 0800 16 November and a return 0800 20
November. Four days underway; nine calendar days (16-21 Nov) required on
schedule
due to on-load and off-load requirements.
----------


Agency                    Funded            Proposed               TOTAL
------                    ------            --------               -----
 NOAA                      32.0                 0.0                32.0
 NSF                      100.0                 0.0               100.0
 Other                     22.0                 0.0                22.0
------                     -----               -----               -----
 TOTAL                    154.0                 0.0               154.0